GENERAL CONSTRUCTION WORKS CARRIED OUT IN DECEMBER 2024

Works to be performed in December:

Building 1:

  • Section 1:Plastering works are being carried out on the 4th and 5th floors. Plumbing works are underway on the 4th and 5th floors. Installation of window structures on the 5th and 6th floors. Electrical installation works on the 5th to 7th floors.

  • Section 2:Wall masonry is being done on the 6th and 7th floors. Roof waterproofing installation is in progress.

Building 2:Construction of the building frame above the 0.00 mark. Installation of vertical waterproofing for the building.

Building 3:Construction of the building frame above the 0.00 mark. Installation of vertical waterproofing for the building.