GENERAL CONSTRUCTION WORKS CARRIED OUT IN FEBRUARY 2025
Building 1
Section 1:
Electrical installation work on the 7th floor has been completed. Plumbing work on the 7th floor is being finalized.
Section 2:
Masonry work on the 2nd floor is completed. Installation of window structures on the 3rd floor has begun. Sewage riser installation is in progress. Plastering work continues on the 6th floor. Electrical installation is underway on the 5th floor.
Building 2
Construction of the monolithic frame on the 2nd floor is ongoing. Masonry work for ventilation shafts on the 2nd floor is in progress.
Building 3
The monolithic frame on the 3rd floor is being installed. Brickwork is in progress on the basement and 1st floors. Ventilation shaft masonry on the 2nd floor is underway.