GENERAL CONSTRUCTION WORKS CARRIED OUT IN JANUARY 2025
Building 1, Section 1:
Plastering work on the 6th floor has been completed.
Installation of heating distribution on the 6th floor is finished.
Wiring for general area lighting (GAL) and apartments has been completed.
Building 1, Section 2:
Masonry work for internal partitions on the 5th floor is finished.
Installation of sewage risers is completed.
Electrical wiring on the 1st floor has been completed.
Building 2:
Construction of vertical structures on the 2nd floor is in progress.
Building 3:
Construction of vertical structures on the 2nd floor is in progress.