GENERAL CONSTRUCTION WORKS CARRIED OUT IN MARCH 2025

Building 1

Wall plastering in Section 2 on the 5th floor.

Installation of the heating system in Section 2 on the 2nd floor.

Electrical installation work in Section 2 on the 5th floor.

Installation of ventilation ducts in the parking area.


Building 2

Completion of roofing work in Section 2.

Installation of the slab for the 4th floor.

Masonry work on the 1st floor.

Installation of ventilation ducts on the 2nd floor.


Building 3

Installation of the slab for the 3rd floor.

Installation of ventilation ducts on the 2nd floor.

Masonry work on the 1st floor.